12 Points to Check For PCC in The Foundation | Checklist For PCC Below The Footing | Procedure of Foundation PCC

In this article, we explain important 12 points that should be checked before PCC work in the foundation

12 Points to Check For PCC in The Foundation

    Strata for PCC Foundation

    12 Points To Check For Pcc In The Foundation | Checklist For Pcc Below The Footing | Procedure Of Foundation Pcc.

    Once footing excavation is complete then you should check for the SBC (soil bearing capacity) of soil or strata for the laying of the PCC Foundation.

    If there are deep pockets in the strata then it should be filled with plum concrete before doing PCC work.

    Strata For Pcc Foundation

    For the residential buildings type of building having low bearing capacity soil, boulder soling is preferred by expert civil engineers and experience constructors for the stabilization of the foundation.

    Footing Layout Marking for PCC Formwork

    The centerline of the column is marked & the excavated pit is checked for its correct position. The outline of the foundation is checked to mark the boundary of PCC.

    Footing Layout Marking For Pcc Formwork

    If the excavation is done by the JCB, the size of the pit may be inaccurate. In that case, you have to fix the formwork box for the casting of PCC work.

    Cleaning Excavated Pit

    Remove all the unwanted materials such as organic debris, rocks, formwork pieces, loose soils, etc. should be removed from the footing pit and make it clean for level work.

    Levelling

    The top level of the PCC is marked at the 4 corners of the foundation pit. The depth of the PCC is considered from the highest level point of the uneven strata.

    For eg., if the PCC depth is 100mm., the top level of PCC is marked at 100mm. above the upper portion of the strata.

    Dewatering

    Dewatering

    If there is any seepage of water occurs at the footing pit, a sump/motor is set at the lowest corner of the strata for the dewatering of the footing pit. 

    While pouring the concrete, it should be checked that the water level should not be more than the strata level. The dewatering process is continued until the PCC gains its initial setting time.

    Sprinkling

    If the strata of the excavated pit is dry without any moisture content then you have to sprinkle water in Excavated Pit before concreting. Otherwise, the strata or soil surface absorbs all most water from the poured PCC concrete, to make it weak having a lower strength.

    Concrete Mix Design

    The grade of concrete mix design for the PCC work is checked for its proportion to achieve the required consistency. The W/C ratio is maintained to prevent segregation & bleeding in concrete.

    Pouring

    If the pouring depth is higher than 1.5 meters, a chute arrangement is made to prevent the segregation of concrete in construction.

    Thickness of PCC in Construction

    After pouring work & compaction of concrete is done by vibration of using a concrete vibrator, the top level of the PCC is checked for its required depth, and levelling is done

    Top Finnined PCC Surface

    The top concrete surface is finished by using a levelling metal Patti & lineout string or any method.

    The uniform top-level is checked diagonally by holding the string at the PCC corners.

    Curing of Concrete

    The curing of Concrete process starts from the next day to achieve the required strength of concrete structural elements.

    â™› Follow Us â™›
    FAQ 1: Thickness of PCC in Construction

    After pouring work and compaction of concrete is done by vibration of using a concrete vibrator, the top level of the PCC is checked for its required depth, and levelling is done 

    FAQ 2: Footing Layout Marking for PCC Formwork 

    The centerline of the column is marked and the excavated pit is checked for its correct position. The outline of the foundation is checked to mark the boundary of PCC.Footing Layout Marking for PCC FormworkIf the excavation is done by the JCB, the size of the pit may be inaccurate. In that case, you have to fix the formwork box for the casting of PCC work.

    Civil Experience
    Author Aakash Dudhat

    It is my pleasure to welcome you to civilexperiences.com, a website created and managed by Dudhat Aakash. In addition to having a Bachelor's degree in Civil Engineering

    Leave a Comment