How to take out quantity of concrete for 1 cubic meter? | Concrete Quantity Calculation

Rate this post

In today civil experience article, we will explain How to take out quantity of concrete for 1 cubic meter, Also we publish Concrete Quantity Calculation calculator soon so read this article and join for the latest updates

Here the question is incomplete means Civil Engineers or Estimation Engineers required more data regarding work so that they can calculate the quantity of concrete for 1 cubic meter.

Civil Experience provides all possible solutions for M5, M7.5, M10, M15, M20, M25 so you get you all answer in one place.

After the M25 grade of concrete, you must create your mix design as per requirement and site and materials but don't worry about calculation Civil Experience already provide Best Concrete Mix Design As Per IS Code Excel Sheet

    Table of Contents

    Quantity of Concrete For 1 Cubic Meter | Concrete Quantity Calculation

    Now we directly come to a solution, Required data for Concrete calculation  is provided below

    • Volume of Concrete
    • Grade of Concrete

    Here volume of concrete is 1 cubic meter but we must need the grade of concrete to calculating cement, calculating sand, and aggregate so here Civil Experience provides all possible concrete mix calculation quantities.

    Before starting the calculation of concrete quantity of particular grade of concrete we explain which you get by those answers and which quantion is to solve

    • How to take out quantity of concrete for 1 cubic meter?
    • How many cement bags do I need?
    • Cement quantity need for construction of 1 cubic meter?
    • Cement Required For 1 Cubic Meter
    • Cement required for 1 cubic meter m25 concrete
    • Cement required for 1 cubic meter m20 concrete
    • Cement required for 1 cubic meter m15 concrete
    • Sand required for 1 cu.m concrete
    • Aggregate needed for 1 meter cube concrete… etc
    • We calculate concrete calculation in cft and cubic meter also in kg for you
    Note

    How to calculate cubic meter of concrete for M15 grade of Concrete

    How to calculate cubic meter of concrete for M15 grade of Concrete | How to take out quantity of concrete for 1 cubic meter? | Concrete Quantity Calculation
    How to calculate cubic meter of concrete for M15 grade of Concrete

    M15 Mix design ratio for M15 grade of concrete is 1:2:4 (1 part cement:2 part of fine aggregate:4 part of course aggregate) sum of ratio is 7.

    How Many Bags of 50kg Cement in 1 cubic meter for M15 grade of Concrete

    Cement bags required for 1 cubic meter of M15 concrete grade is 6.334 â‰ˆ 7 so 7 cement bags are needed of 50kg cement in 1 cubic meter

    No of cement bags in 1m3 concrete for M15 grade of concrete is 7 cement bags

    Cement required in KG

    316.8 kg

    Cement required in cubic feet

    7.77 cuf

    Cement required in cubic meter

    0.22 cum

    Fine Aggregate/Sand Quantity Required for M15 grade of Concrete

    Fine Aggregate required in KG

    600 kg

    Fine Aggregate required in cubic feet

    15.54 cuf

    Fine Aggregate required in cubic meter

    0.44 cum

    Coarse Aggregate Quantity Quantity Required for M15 grade of Concrete

    Coarse Aggregate required in KG

    1408 kg

    Coarse Aggregate required in cubic feet

    3107 cuf

    Coarse Aggregate required in cubic meter

    0.88 cum

    How to calculate cubic meter of concrete for M20 grade of Concrete

    M20 Mix design ratio for M20 grade of concrete is 1:1.5:3 (1 part cement:1.5 part of fine aggregate:3 part of course aggregate) sum of ratio is 5.5.

    How Many Bags of 50kg Cement in 1 cubic meter for M20 grade of Concrete

    How to calculate cubic meter of concrete for M20 grade of Concrete | How to take out quantity of concrete for 1 cubic meter? | Concrete Quantity Calculation`
    How to calculate cubic meter of concrete for M20 grade of Concrete

    Cement bags required for 1 cubic meter of M20 concrete grade is 8.064 ≈ 8 so 8 cement bags are needed of 50kg cement in 1 cubic meter

    No of cement bags in 1m3 concrete for M20 grade of concrete is 8 cement bags

    Cement required in KG

    403.2 kg

    Cement required in cubic feet

    9.89 cuf

    Cement required in cubic meter

    0.28 cum

    Fine Aggregate/Sand Quantity Required for M20 grade of Concrete

    Fine Aggregate required in KG

    630 kg

    Fine Aggregate required in cubic feet

    14.83 cuf

    Fine Aggregate required in cubic meter

    0.42 cum

    Coarse Aggregate Quantity Quantity Required for M20 grade of Concrete

    Coarse Aggregate required in KG

    1344 kg

    Coarse Aggregate required in cubic feet

    29.66 cuf

    Coarse Aggregate required in cubic meter

    0.84 cum

    How to calculate cubic meter of concrete for M25 grade of Concrete

    M25 Mix design ratio for M25 grade of concrete is 1:1:2 (1 part cement:1 part of fine aggregate:2 part of course aggregate) sum of ratio is 4.

    How Many Bags of 50kg Cement in 1 cubic meter for M25 grade of Concrete

    How to take out quantity of concrete for 1 cubic meter? | Concrete Quantity Calculation
    How to calculate cubic meter of concrete for M25 grade of Concrete

    Cement bags required for 1 cubic meter of M25 concrete grade is 11.088 ≈ 11 so 11 cement bags are needed of 50kg cement in 1 cubic meter

    No of cement bags in 1m3 concrete for M25 grade of concrete is 11 cement bags

    Cement required in KG

    554.4 kg

    Cement required in cubic feet

    13.59 cuf

    Cement required in cubic meter

    0.385 cum

    Fine Aggregate/Sand Quantity Required for M20 grade of Concrete

    Fine Aggregate required in KG

    577.5 kg

    Fine Aggregate required in cubic feet

    13.59 cuf

    Fine Aggregate required in cubic meter

    0.385 cum

    Coarse Aggregate Quantity Quantity Required for M20 grade of Concrete

    Coarse Aggregate required in KG

    1232 kg

    Coarse Aggregate required in cubic feet

    27.1887 cuf

    Coarse Aggregate required in cubic meter

    0.77 cum

    Faq For Quantity of Concrete of 1 cubic meter

    How Many Bags of 50kg Cement Required in 1 cubic meter for M15 grade of Concrete?

    Cement bags required for 1 cubic meter of M15 concrete grade is 6.334 ≈ 7 so 7 cement bags are needed of 50kg cement in 1 cubic meter.

    How many Fine Aggregate/Sand Quantity Required for M15 grade of Concrete?

    Fine Aggregate required in KG 600 kg for M15 grade of Concrete, Fine Aggregate required in cubic feet 15.54 cuf for M15 grade of Concrete, The fine Aggregate required in cubic meter is 0.44 cum for the M15 grade of Concrete.

    How many Coarse Aggregate Quantity Quantity Required for M15 grade of Concrete?

    Coarse Aggregate required in KG is 1408 kg for M15 grade of Concrete, Coarse Aggregate required in cubic feet is 3107 cuf for M15 grade of Concrete, The coarse Aggregate required in cubic meters is 0.88 cum for the M15 grade of Concrete.

    How Many Bags of 50kg Cement in 1 cubic meter Required for M20 grade of Concrete?

    Cement bags required for 1 cubic meter of M20 concrete grade is 8.064 ≈ 8 so 8 cement bags are needed of 50kg cement in 1 cubic meter.

    How many Fine Aggregate/Sand Quantity Required for M20 grade of Concrete?

    Fine Aggregate required in KG is 630 kg for M20 grade of Concrete, Fine Aggregate required in cubic feet is 14.83 cuf for M20 grade of Concrete, The fine Aggregate required in cubic meters is 0.42 cum for the M20 grade of Concrete.

    How many Coarse Aggregate Quantity Quantity Required for M20 grade of Concrete?

    Coarse Aggregate required in KG is 1344 kg for M20 grade of Concrete, Coarse Aggregate required in cubic feet is 29.66 cuf for M20 grade of Concrete, The coarse Aggregate required in cubic meters is 0.84 cum for the M20 grade of Concrete.

    How Many Bags of 50kg Cement in 1 cubic meter for M25 grade of Concrete?

    Cement bags required for 1 cubic meter of M25 concrete grade is 11.088 ≈ 11 so 11 cement bags are needed of 50kg cement in 1 cubic meter. No of cement bags in 1m3 concrete for M25 grade of concrete is 11 cement bags.

    How many Fine Aggregate/Sand Quantity Required for M20 grade of Concrete?

    Fine Aggregate required in KG is 577.5 kg for M20 grade of Concrete, Fine Aggregate required in cubic feet is13.59 cuf for M20 grade of Concrete, The fine Aggregate required in cubic meters is 0.385 cum for the M20 grade of Concrete.

    How many Coarse Aggregate Quantity Quantity Required for M20 grade of Concrete?

    Coarse Aggregate required in KG is 1232 kg for M20 grade of Concrete, Coarse Aggregate required in cubic feet is 27.1887 cuf for M20 grade of Concrete, The coarse Aggregate required in cubic meters is 0.77 cum for the M20 grade of Concrete.

    Also Read: How to take out quantity of concrete for 11.7 cubic meter?