Estimation and Costing MCQs | Civil Engineering MCQs for Estimation and Costing

Estimation and Costing MCQs | Civil Engineering MCQs for Estimation and Costing. test series mcq for exam preparation. Which you do not want to miss.

Estimation and Costing MCQs | Civil Engineering MCQs for Estimation and Costing

In this article, you will get all Estimation and Costing MCQs with answers for best practices for competitive exams to crack competitive exams will always update our article and add more and more MCQ so bookmark and share the civil experience site for future learning.

Here in civil experience best civil engineering website, you will get the best learning and study materials, article, pdf, ppt, reports, etc for Estimation and Costing and others too so must join a civil experience blog and learn every day

Join us
LinkedIn | Google News | Telegram | Facebook | Instagram | Twitter | YouTube | Quora

Maximum surface drying time for class C and Class D type plastic emulsion paint is





ANSWER = [B] 90 minute

The correct answer for Maximum surface drying time for class C and Class D type plastic emulsion paint is 90 minutes.

If the optimistic time, most likely and pessimistic time for activity A are 4.6 and 8 respectively. What would be expected time for completion of activity A?





ANSWER= [B] 6 days
If the optimistic time, most likely and pessimistic time for activity A are 4.6 and 8 respectively. Than expected time for completion of activity A is 6 days.

Which of the following activities is NOT included in cash flow?





ANSWER = [B] Estimating and costing activities


357k people like this. Be the first of your friends.

You may like these posts

  1. To insert a code use <i rel="pre">code_here</i>
  2. To insert a quote use <b rel="quote">your_qoute</b>
  3. To insert a picture use <i rel="image">url_image_here</i>

Most Demanded by User

Website is locked Press Subscribe or Share to unlock!